Delhi Metro Phase-IV: Work On RK Ashram-Janakpuri Route To Start In December

November 01 2019   |   Surbhi Gupta

With authorities releasing Rs 800 crore for this purpose, construction work on the Delhi Metro Phase-IV is likely to start in December this year. The construction work may first start on the Janakpuri-RK Ashram route, the longest corridor under this phase. Tenders will be soon floated for two other priority corridors, Aerocity-Tughlaqabad and Majlis Park-Maujpur. 

DMRC Starts Preparatory Work For Delhi Metro Phase-IV

After Supreme Court order on July 8, 2019 to go-ahead with the construction of the Delhi Metro’s 104-km Phase IV, the Delhi Metro Rail Corporation has started preparatory work for its much-delayed Phase-IV project. The project is scheduled to be completed in five years from the date of start of work.

The Union Cabinet on March 7 has already approved three out of the proposed six routes of  the Delhi Metro Phase-IV. The three corridors that received the Cabinet's go-ahead include Mukundpur-Maujpur, RK Ashram-Janakpuri West and AeroCity-Tughlakabad corridor. The new phase is expected to connect Delhi to the farther corners of the national capital region (NCR) . 

It was in December last year that the Delhi government had approved all the six proposed corridors of the 104-km project. 

However, with Cabinet's approval, the Phase-IV will only be 61.679-km with 46 Metro stations, of which 17 will be elevated. The total cost of the project is pegged around Rs 25,000 crore, which will be partially shared by the Delhi government. 

The Delhi Metro’s Phase-IV was planned to provide last mile connectivity to the new housing hubs in the NCR. According to the government, there will be 17 underground and 29 elevated stations along the the corridors. Once completed it is expected to cater to nearly 15 lakh passengers daily.

Routes approved by the Cabinet

*Tughlakabad to Aerocity (20 km) - There will be 15 stations on this route and will connect the Faridabad region with the airport. 

*Mukundpur to Maujpur (12 km) - There will be 6 stations on this route and will connect east Delhi with the northern region. 

*Janakpuri to RK Ashram (28 km) - There will be 25 stations on this route. This two stations are also connected through Blue Line which passes through Karol Bagh, Patel Nagar. 

Tughlakabad to AerocityMukundpur to MaujpurJanakpuri to RK Ashram
AerocityYamuna ViharRK Ashram
MahipalpurBhajanpuraMotia Khan
Vasant Kunj Sector DKhajuri KhasSadar Bazaar
MasoodpurSoorghatPul Bangash
KishangarhJagatpur VillageGhanta Ghar/Sabzi Mandi
MehrauliBurariRajpura
Lado Sarai Derawal Nagar
Saket Ashok Vihar
Saket G Block Azadpur
Ambedkar Nagar Mukundpur
Khanpur  Bhalaswa
Tigri  Mukarba Chowk
Anandmayee Marg Junction  Badli Mor
Tughlakabad Railway Colony  North Pitampura
Tughlakabad  Prashant Vihar
  Madhuban Chowk
  Deepali Chowk
  Pushpanjali Enclave
  West Enclave
  Mangolpuri
  Peeragarhi Chowk
  Paschim Vihar
  Meerabagh
  Keshopur
  Krishan Park Ext.
  Janakpuri West

Timeline

June 2016: A Detailed Project Report (DPR) for the Phase-IV received approval.

January 2017: In-principle approval from finance ministry

December 2018: Delhi government approves Metro Phase IV

March 2019: Union Cabinet approves three out of six corridors of Phase IV